Planning stage
Date | Task |
---|---|
19 Jun 2014 | Land settled |
19 Aug 2014 | Tender appointment |
29 Sep 2014 | Color appointment |
Contract appointment |
Building stage
Date | Task |
---|---|
1 Jul 2014 | Land available for building |
26 Jan 2015 | Building Start |
28 Jan 2015 | Land Cut Completed |
06 Feb 2015 | Pier being laid |
09 Feb 2015 | Drains completed |
12 Feb 2015 | Slab completed |
16 Feb 2015 | Frame started |
3 Mar 2015 | Frame complete (estimate) |
2 Mar 2015 | Frame complete |
2 Mar 2015 | Enclose stage start |
24 Mar 2015 | Bricklayer start |
7 April 2015 | Plasterwork start |
16 April 2015 | Enclosed stage completed |
20 April 2015 | Fix stage start |
20 April 2015 | Painter start |
1st May 2015 | Carpenter start |
4 May 2015 | Tiler start |
21 May 2015 | Fix stage completed |
25 May 2015 | Complete stage start |