Building timeline


Planning stage

Date Task
19 Jun 2014 Land settled
19 Aug 2014 Tender appointment
29 Sep 2014 Color appointment
Contract appointment


Building stage

Date Task
1 Jul 2014 Land available for building
26 Jan 2015 Building Start
28 Jan 2015 Land Cut Completed
06 Feb 2015 Pier being laid
09 Feb 2015 Drains completed
12 Feb 2015 Slab completed
16 Feb 2015 Frame started
3 Mar 2015 Frame complete (estimate)
2 Mar 2015 Frame complete  
2 Mar 2015 Enclose stage start
24 Mar 2015  Bricklayer start
7 April 2015  Plasterwork start
16 April 2015 Enclosed stage completed
20 April 2015 Fix stage start
20 April 2015 Painter start
1st May 2015 Carpenter start
4 May 2015 Tiler start
21 May 2015 Fix stage completed
25 May 2015 Complete stage start